Baglan Bay Innovation Centre

Project Case Study:No 2 Bucket Wheel Reclaimer (BWR)

Key Project Details

Client: Tata Steel UK
Location: Port Talbot
Project: No 2 Bucket Wheel Reclaimer (BWR) Drive Upgrade
Date: 2023 – 2024
Engineer: Ingleside Engineering Ltd

Project Background

Tata Steel’s Port Talbot works is one of the UK’s largest integrated steelmaking sites. Within its harbour area, large bucket wheel reclaimers (BWRs) handle raw materials before transfer to the processing plants. Over time, the existing gearbox-driven system on the No. 2 BWR became less efficient and increasingly difficult to maintain.

To enhance reliability and extend the life of this critical equipment, Tata Steel commissioned Ingleside Engineering Ltd to design and deliver an upgrade from the existing gearbox drive to a Hägglunds/Rexroth hydraulic motor drive system.

The project also required a new steel platform and access bridge to support the hydraulic power unit and improve maintenance accessibility.

Key Challenges

  • Structural Integration: The new drive and power pack needed to interface precisely with the existing bucket wheel framework, ensuring minimal disruption to the machine’s geometry and operation.
  • Machine Balance: Removal of the original gearbox and addition of new hydraulic components affected the machine’s balance. Detailed counterweight calculations were undertaken to ensure stability and load distribution.
  • Access and Safety: Tata Steel required improved maintenance access, including new walkways, guardrails, and an ergonomic layout for safer operation.
  • Site Constraints: All components had to be designed for efficient on-site installation, including bolt-on and weld-on assemblies that could be completed within a limited shutdown window.

Investigation & Analysis

  • Reviewed existing machine configuration and operational load data from Tata Steel.
  • Conducted detailed assessments of structural connections and drive mounting points.
  • Modelled load paths and moments to verify compatibility with the new hydraulic drive.
  • Performed counterweight analysis to ensure overall system balance post-upgrade.
  • Evaluated access, safety, and maintenance requirements for platform integration.

Engineering Design Solution

Ingleside Engineering developed a fully integrated solution combining 3D structural modelling, mechanical interface design, and detailed fabrication documentation.

Design Highlights:

  • 3D Tekla Model: Comprehensive model of the upgraded drive structure and associated components, ensuring alignment accuracy and clash-free installation.
  • New Support Platform: Constructed from UB254×146×31 and UB305×165×40 universal beams with gusset plates and tie connections for rigidity.
  • Maintenance Access Bridge: New access link connecting directly to the existing bucket wheel walkway.
  • Hydraulic Drive Mounts: Custom torque arm and mounting assemblies designed for on-site welding to Hägglunds/Rexroth specifications.
  • Fabrication Detailing: Drawings and material schedules extracted directly from the Tekla model for manufacture and assembly precision.

All designs were documented within the C407 Design Brief and related layout and calculation drawings (IEL-C407-001 and IEL-C407-002).

Implementation

  • Issued full design brief, 3D models, and fabrication drawings to Tata Steel.
  • Coordinated with on-site teams to plan efficient removal and installation sequencing.
  • Provided technical support during installation and welding of hydraulic mounts.
  • Verified alignment and balance post-installation to meet operational standards.

Project Outcomes

  • Reliability: The new Hägglunds/Rexroth hydraulic motor provides a robust, low-maintenance solution.
  • Safety: New access platforms and guardrails ensure safer working conditions during maintenance.
  • Structural Balance: Counterweight calculations verified through design analysis and testing.
  • Maintainability: Modular platform design simplifies inspection and servicing.
  • Efficiency: 3D modelling and prefabrication enabled faster, error-free site installation.

Key Results

Objectives

  • RReplace obsolete gearbox drive
  • RImprove equipment reliability
  • REnsure system stability
  • REnhance operator safety
  • RMinimise downtime

Results

  • AHydraulic motor system successfully installed
  • ARobust and low-maintenance solution achieved
  • ACounterbalance verified through analysis
  • ANew walkways and guardrails installed
  • APrefabrication and modular assembly reduced shutdown time