Project Case Study:36" COG Main Replacement
Key Project Details
Location: No 4 Bridge to Diesel Loco Shed
Project: Replacement of 36” Coke Oven Gas Main and Associated Support Structures
Date: February 2022
Engineer: Ingleside Engineering Ltd
Project Background
The 36-inch Coke Oven Gas (COG) main forms a critical part of Tata Steel Port Talbot’s gas distribution network, supplying various process plants across the site. Routine thickness testing identified significant wall loss in a section of the main between Bridge No.4 and the Diesel Loco Shed (DLRS). To maintain system reliability and safety, this section required full replacement.
Ingleside Engineering Ltd was appointed to develop the temporary works and support modifications necessary to replace the affected section with minimal plant outage and disruption to production.
Key Challenges
- Replacement required within an operational brownfield area of the live steelworks.
- Complex routing of the 36” gas main supported on a series of two-leg and four-leg trestles.
- Limited access and headroom beneath existing structures.
- Requirement to maintain bridge stability during pipe removal and installation.
- Outage time constraints demanding a rapid, safe, and controlled installation sequence.
Key Challenges
- Conducted site survey and condition assessment of all trestle supports and bridge connections.
- Carried out finite element analysis (SkyCiv) on each trestle type under load cases for existing, removal, and installation conditions.
- Identified need for temporary bridge support during main removal to ensure no excessive deflection or instability.
- Assessed interaction between old and new pipe routes using Tata Steel drawings:
- 7182-27-00-12-011 – Existing 36” COG Main layout.
- 7182-27-00-12-012 – Route of new 36” COG Main adjacent to Bridge No.4.
Key Challenges
- Developed bespoke temporary trestle modifications to allow safe removal and replacement of the main.
- Designed and validated two-leg and four-leg trestles for all affected sections using both Scenario 1 (pre-replacement) and Scenario 2 (post-replacement) load cases.
- Introduced temporary bridge support frames to maintain structure stability during removal of the existing main.
- Established a defined removal sequence for the Bridge No.4 section to control load transfer.
- Coordinated new pipe alignment and support positioning to suit the revised route and minimize structural adjustments.
- Produced comprehensive drawing and calculation packages, including:
- C323-IEL-001 – 36” COG Main Supports and Trestle Layout.
- IEL-C323-001 – 36” COG Main Removal Sequence (Bridge Section).
- Associated FEA summary and SkyCiv analysis reports for each trestle configuration.
Key Challenges
- Issued full temporary works design documentation and construction sequence.
- Supported Tata Steel and site contractors during installation planning and execution.
- Ensured structural verification and authorisation at each stage prior to lift and replacement operations.
- Sequenced replacement activities to maintain operational continuity and minimise outage duration.
Key Challenges
- Safe and efficient replacement of the 36” Coke Oven Gas main section completed to schedule.
- Bridge and trestle structures remained within allowable deflection and stress limits throughout works.
- Temporary works enabled removal and installation without unplanned outages.
- All designs and calculations met Tata Steel engineering standards and BS 5975 compliance.
- Project delivered with zero incidents and minimal disruption to adjacent plant operations.
Key Results
Objectives
- RReplaced degraded section of 36" COG main
- RMaintain bridge and trestle integrity
- RControl outage duration
- REnsure structural and safety compliance
- RDeliver project without incidents
Results
- ASuccessfully completed
- AVerified through analysis and monitoring
- AAchieved - minimal downtime
- ABS 5975 compliant
- AZero safety or quality issues